Interior Construction Timeline

 Construction of the house started on the 23rd of January.

 

The tile work around the gas fireplace in the living room is complete.

May 28, 2002

Wiring for the phone and computer network is in process.

May 28, 2002

The tile in the master shower and bath is underway. (Colors in the photo are not exact)

May 23, 2002

The tile in the first floor bathroom is installed.

May 20, 2002

The maple floor on the first floor is installed, but not finished. The second floor will be bamboo and will be installed in early June.

May 20, 2002

The interior doors have been installed. These mahagony doors lead to the first floor study.

May 15, 2002

The trim was delivered from Acorn today and is stored in a storage trailer on site.

May 14, 2002

The sheet rock and taping are just about complete.

April 18, 2002

The rough-in phase is now complete. The building inspector approved the work to date earlier today.

The schedule calls for insulation to begin on the 29th and for sheet rock to begin on May 1st.

Week of April 8

The AC install continues. The electric installation is underway as is the install of the central vacuum system.

April 5, 2002

Installation of the air conditioning continues. The first floor is just about complete. Work will continue on the second and third floor this week.

April 4, 2002

The rough in of the plumbing was started yesterday. It is about 75% complete. The plumber will return next week to work on the gas (propane) lines.

March 29, 2002

The air conditioning system installation started today. The system is a high velocity sustem that uses a much higher air pressure. This allows for substantially smaller ducts and much smaller vents.

March 26, 2002

The stairway from the second to third floor was installed today. This photo is taken for the third floor looking down. The ladder is on the first floor. The stairwayis open to all three levels.

March 22, 2002

The stairway from the first to second floor has been installed.

March 22, 2002

A view through the living room windows. The winds outside were quite strong today as shown by the surf in the distance.

March 22, 2002

The interior framing is just about complete. This view is from the second floor hall towards the master bedroom.

March 22, 2002

This view is from the landing on the stairs.

 

  
In This Section

Before Pictures
House Plans
Pre-Demolition
Demolition Day 1-2
Demolition Day 3-4
Demolition Day 5-7
Foundation
Delivery Day
Construction
Interior
Kitchen
Landscaping

What's New

The Bikini Atoll trip section now has island and underwater photos! 
sunset
 

Copyright 2004-2005 - Bob Liptrot

 
cool